NorthWestern Energy

Licensing Studies & Documents,
7/1/04 to 12/17/07


October 1, 2007
PPL Montana comments on the FERC Mystic EA
» download PDF (45k)

September 17, 2007
Letter from Jon Jourdonnais to Kimberly D. Bose, Secretary to FERC. Re: Mystic Lake Project 2301 - PPL Montana corrections to
Exhibits A and G
» download PDF (26k)

September 14, 2007
CRM Final Programmatic Agreement, submitted to FERC
» download PDF (323k)

June 2007
Hydro Review Article of the Mystic Lake ILP Experience
» download PDF (170k)

May 1, 2007
Letter from Jon Jourdonnais to Magalie Roman Salas, Secretary to FERC. Re: PPL Montana corrections to Exhibit G TIFF images for Mystic Lake Project (P-2301-022)
» download PDF (45k)

February 20, 2007
Mystic Process Plan & Communications Protocol
» download PDF (37k)

December 15, 2006
Mystic Project Final License Application:
PPL Montana Cover Letter to FERC (Public)
» download PDF (120k)

Volume I - Exhibits A-D, H (Public)
» download PDF (1.93m)

Volume IA - Exhibit E (Public)
» download PDF (3.05m)

Volume IIA - Exhibit E Figures (Non-Internet Public)
(contact Jon Jourdonnais at jon.jourdonnais@northwestern.com for
an electronic copy)

Volume IIB - Exhibit G (Non-Internet Public)
(contact Jon Jourdonnais at jon.jourdonnais@northwestern.com for
an electronic copy)

Volume III - Exhibit F (Critical Energy Infrastructure Information)
(contact the Federal Energy Regulatory Commission for a copy)

Volume IV - Historic Properties Management Plan
(Non-Public Privileged)

Volume V - Historic Properties Programmatic Agreement
(Non-Public Privileged)

June 20, 2007
Recreation, Land Use and Aesthetics Resource Group
Final Meeting Summary
» download PDF (23k)

June 1, 2006
Mystic Lake Preliminary Licensing Proposal
» more info

May 30, 2006
Study No. 18 Addendum - Macroinvertebrate and Sediment Study
» download PDF (1.31m)

April 3, 2006
Letter from Jon Jourdonnais to Magalie Roman Salas, Secretary to FERC. Re: Mystic Lake Project 2301 Integrated Licensing Process: Filing of Study Reports
» download PDF (64k)

April 3, 2006
Study 6. "Hydrologic Characterization of the West Rosebud Creek Bypass Reach Between Mystic Lake Dam and the Powerhouse - April 2006 Final Report"
» download PDF (1.48m)

April 3, 2006
Study 10. "Shoreline Erosion Inventory at Mystic Lake - April 2006 Final Report with Quantitative Analysis"
» download PDF (6.45m)

April 3, 2006
Study 12. "Flow Restoration Action Plan for Flow-line or Penstock Shutoff - April 2006 Supplemental Report, Volume I -Public"
» download PDF (348k)

January 3, 2006
PPL Montana response to USFS letter of December 8, 2005 regarding Mystic hydrology and riparian issues
» download PDF (71k)

December 13, 2005
Letter from Jon Jourdonnais to Magalie Roman Salas, Secretary to FERC. Re: Completion of Study No. 7 - Water Temperature Monitoring for the Mystic Lake Project (2301) per FERC's Integrated Licensing Process
» download PDF (106k)

December 1, 2005
Letter from Jon Jourdonnais to Magalie Roman Salas, Secretary to FERC. Re: Filing as confidential the Mystic Lake Project Cultural Resource Management Inventory and NRHP Evaluation Documentation Historic Plant Operating Facilities under the Integrated Licensing Process
» download PDF (63k)

December 1, 2005
Letter from Jon Jourdonnais to Magalie Roman Salas, Secretary to FERC. Re: Filing as confidential the Mystic Lake Project Cultural Resource Management Archeolgical Report under the Integrated Licensing Process
» download PDF (30k)

November 15, 2005
Study 9 Aerial Survey of the Riparian Corridor - Supplement
» download PDF (12.2m)

November 1, 2005
Initial Study Report Meeting Summary
» download PDF (8.08m)

October 3, 2005
Mystic Lake 2005 Study Results: Studies No. 1-20
» download PDF

March 18, 2005
Letter: Response to Forest Service comments on PPL Montana's Final Mystic Lake Project Study Plan
» download PDF (153k)

March 1, 2005
Mystic Lake Final Study Plan, Volume I - Cover Letter
» download PDF (1.6m)

March 1, 2005
Mystic Lake Final Study Plan, Volume I
» download PDF

Nov. 1, 2004
Mystic Lake Project Proposed Study Plan
» download PDF (2.6m)

July 15, 2004
Mystic Scoping Document I
» download PDF (299k)

July 1, 2004
Mystic PAD FERC Letter and NOI
» download PDF (561k)

July 1, 2004
Mystic PAD Volume 1 Public
» download PDF (5.7m)


Download the free
Adobe Reader to view PDF documents


PUBLIC
REFERENCE
FILES:

Post-Licensing
Reporting Docs,
since 12/17/07

Final Meeting
Summaries

Licensing Studies
& Docs, 7/1/04 to
12/17/07

Pre-Licensing Studies
& Docs, prior to 7/1/04

Mystic Boundary
Wilderness
Resource Library

LINKS FOR
BOATERS:

USGS Streamflow
Gauge for West
Rosebud Creek

Protocol for West Rosebud Creek Whitewater Flow Enhancement

Mystic Lake Pool Elevation

 
Copyright © 2004-2017 NorthWestern Energy
All Rights Reserved.
For questions regarding the content of this site:
Contact NorthWestern Energy.
For general questions about this site:
Contact Webmaster.